Talaat Energy participation in Fabrication, Installation and Commissioning of Njaba Pipeline Ends (Process) Facilities.
Client
Addax Petroleum
Project Scope
- Carry out site survey as per work scope.
- Carry out community settlement.
- Mobilise to site all Equipment/Tools and Personnel.
- Fabrication and installation of production, test and gas-lift manifold at Njaba location as per attached drawing.
- Fabrication and installation of Production Pig-launcher and Gaslift Pig Lifter at Njaba location as per attached drawing.
- Fabrication and Installation of all associated piping and installation to connect the launcher and the Production manifold at Njaba location as per drawing.
- Fabrication and installation of vent stack, vent manifold and associated instrumentation and piping items in accordance with the attached drawings as shown on the attached drawing list.
- Installation of test separator (MB – 110), the hook up to the manifold and the piping for tie back into the bulk line. Fabricating all associated piping and instrumentation items.
- Installation of fuel gas scrubber and associated instrumentation items.
- Installation of wellhead control panel and associated instrumentation and piping items as per attached drawing. Drop protection provided for the wellhead control panel.
- Construction of drain sump and installation of associated pumps at Njaba location as per attached drawings. All associated instrumentation items also installed.
- Fabrication and installation of 5000l water tank and water tank stand at Njaba location as per attached drawing. Installation of water tank and associated utility pumps at Njaba location as per attached drawing. All associated instrumentation and piping also installed.
- Installation of two gas generators with all associated electrical, piping and instrumentation connections as per attached drawings.
- Installation of a chemical injection unit with all associated piping and instrumentation connections
- Fabrication and installation of all piping supports at Njaba location.
- Carrying out all instrumentation, electrical and mechanical work items required to complete the project as per attached drawings.
- Fabrication and installation of 1000L diesel storage tank at Njaba location in accordance with the attached drawings as shown in the drawing list.
- Designing and carrying out of grounding and earthing of all vessels and tanks. Providing lightening protection for the facility.
- Produce fabrication drawing.
- Carrying out all supported work for the forgoing including Hydrotesting, NDT, Coating, Pre-commissioning, Inspection and Testing.
Fabrication, Installation and Commissioning of Njaba Pipeline Ends (Process) Facilities.
- Project Njaba Fabrication, Installation and Commissioning of Njaba Pipeline Ends (Process) Facilities.
- Customer: Adax Petroleum
- Location: Njaba, Nigeria
- Status: Completed